Time: July 2020
The amount of treated waste gas: SVE system: 26m³/min; MPE system: 40m³/min
Main pollution components: hydrogen sulfide, sulfur dioxide, chloroform, dimethyl sulfide, mercaptan and other pollutants
Treatment process: SVE system: gas liquid separation tank, cooling tower, heat exchanger, extraction fan
MPE system: gas liquid separation tank, cold water tower, heat exchanger, extraction fan
Highlights of the project: the skid mounted design of the equipment, high integration, minimum occupation of the site, high degree of automation, and remarkable effect on tail gas treatment with high temperature and large water vapor
Reference emission standard: secondary emission standard of integrated emission standard of air pollutants (gb-16297-1996)